My favorites | Sign in
Project Home Wiki Issues Source
READ-ONLY: This project has been archived. For more information see this post.
Search
for
  Advanced search   Search tips   Subscriptions
Issue 17: launching a baseline activity
2 people starred this issue and may be notified of changes. Back to list
Status:  Fixed
Owner:  vkak...@gmail.com
Closed:  Nov 2011


 
Project Member Reported by vkak...@gmail.com, Oct 4, 2011
On the waterpoints interface, there should be an option to check which waterpoints need base line info carried out.


Oct 6, 2011
Project Member #1 vkak...@gmail.com
due to the inefficiency in gxt check-box selection model this needs to be put in feature release may be. for now we assume all water-point under baseline not done need to be set for baseline activity
Oct 9, 2011
Project Member #2 kayon...@gmail.com
victor i get a null pointer here
Oct 9, 2011
Project Member #3 vkak...@gmail.com
Ronie do you still get the null Pointer? i instead get a connection time out when launching basleine.
Oct 9, 2011
Project Member #4 kayon...@gmail.com
Victor its ok.. I fixed this at r119
Oct 25, 2011
Project Member #5 kayon...@gmail.com
 Issue 1  has been merged into this issue.
Nov 13, 2011
Project Member #6 vkak...@gmail.com
(No comment was entered for this change.)
Status: Fixed

Powered by Google Project Hosting