Issue 2: Release Dates not propagating from Child to Parent
Status:  New
Owner: ----
Reported by mor...@apigee.com, Oct 14, 2011
What steps will reproduce the problem?
1. Create a release in a child project. 
2. Add a release date to the Release
3. See Release in Parent.
4. Note no date in parent.
5. Return to child and note the date is gone.

What is the expected output? What do you see instead?
Dates assigned to Releases should stick between projects.  Instead, the date is being wiped out by the sync.

What version of the product are you using? On what operating system?
Just installed the latest MasterControl version on 10/14.  

Please provide any additional information below.




Oct 14, 2011
#1 mor...@apigee.com
Also, dates don't propagate from parent to child either.  Wasn't until after I filed this that I realized it seems to be lost in the synchronization.