Here is a list of the tasks accomplished so far along with the (approximate) date of their accomplishment.
(last update Thursday, the 12th of May, 2011)
List of accomplished tasks
| Date | Task(s) accomplished |
| Oct 23, 2010 | Topic chosen (ADAS). |
| Oct 30, 2010 | Cameras, networking, and server added to the project. |
| Nov 02, 2010 | Mailing list (Google group) created. |
| Jan 19, 2011 | Create PCB board for GPS module. |
| Jan 22, 2011 | GPS module is working fine. |
| Feb 03, 2011 | SVN repository (embedded system code) created. |
| Feb 09, 2011 | NMEA code (GPS) parser. |
| Feb 20, 2011 | Server is built. |
| Mar 03, 2001 | Logging mechanism was added to the project to debug the code. |
| Mar 05, 2011 | Ping sensor gives valid measurements. |
| Mar 12, 2011 | Lidar and embedded system board purchase are canceled from the project due to many problems. |
| Mar 14, 2011 | GPS process implemented. |
| Mar 15, 2011 | Parent (Main) process implemented. |
| Mar 22, 2011 | Database and login page are created. |