Issue 7: Preliminary Design Report: Gantt Chart
1 person starred this issue and may be notified of changes. Back to list
 
Project Member Reported by ar...@zips.uakron.edu, Sep 7, 2012
Description of the task to be completed:
The Gantt Chart as part of the preliminary design report needs to be finalized. This should be done using Microsoft Project.

Who is responsible for completing this task:
Megel is responsible for this task.

When must this task be completed by:
This task needs to be completed by noon on Wednesday, Sept 12th.

Additional Information:
Here is the agreed upon schedule through the midterm report that we came up with during our 9-7-2012 meeting.
Design Spec 
  Hardware Requirements
    Mechanical - Megel
    Electrical - Roger
  Software Requirements
    Locomotive - Andrew
    Sensor I/O - Nate
Midtern Design Gantt - Megel
Design Calculations
  Electrical Calculations
    Computing - Andrew
    Control Systems - Nate
    Power, Voltage, Current - Roger
    Radiation - Megel
    Thermal - Megel
  Mechanical Calculations:
    Structural Considerations - Megel
    System Dynamics - Nate
Block Diagram Level 1
  Hardware - Roger
  Software - Andrew
Block Diagram Level 2
  Hardware - Roger
  Software - Andrew
Sep 21, 2012
Project Member #1 ar...@zips.uakron.edu
This has been completed.
Status: Done