Sprint 8 plan : 16 Nov - 27 Nov
Updated Nov 30, 2009 by gklyn...@gmail.com

Introduction

The main goals for this sprint are:

  • to complete the back-end storage interface work started in the previous sprint
  • to improve the online prototype demonstrator for project evaluation (mainly, create a new Shuffl workspace with instructions displayed for doing the various things that Shuffl can do.) Also, notes for installing eXist and Shuffl on a new system
  • If possible, install a copy of Shuffl and eXist on a machine in CH's workgroup
  • final reporting and project wrap-up

Current milestone

Month Activity Deliverables
5: 27Nov 16days Create promotional materials (webcast, dissemination, demonstrations, etc.). Establish a long-term home for the demo service. Ensure that users with whom we have engaged are comfortable with what is available as this project winds down. Public repository contains fully tested software, documentation, promotional materials, deployment instructions, examples, etc., in a state suitable to support ongoing open community development.

Current sprint

Sprint 8 16 Nov - 27 Nov 8 days sprint 8 plan

Previous sprint plan: SprintPlan_7.

Project outline plan: ProjectPlanOutline_200906_200911.

User stories and activities

Activity number Description Effort est Effort actual Target date Completion date
1. Project administration 1.7 1.7
1.1. Sprint 8 plan 0.2 0.2 16-Nov-2009 16-Nov-2009
1.2. Sprint 8 review (retrospective) and final project report notes 0.3 0.2 27-Nov-2009 30-Nov-2009
1.3. Sustainability plan review/stabilize 0.25 0.2 27-Nov-2009 18-Nov-2009
1.4. Miscellaneous admin, email, etc 0.75 0.9 -- --
1.5. Sprint 7 review (retrospective) 0.2 0.2 13-Nov-2009 16-Nov-2009
2. Community engagement and dissemination 0.5 1.4
2.1 Other use cases -- -.- (ongoing) --
2.2 Install/demo system for Chris Holland 0.5 -.- 27-Nov-2009 --
2.3 Demonstrator documentation 0.5 0.2 27-Nov-2009 --
2.4 Other meetings and dissemination -.- 1.2 -- --
3. Technical development 4.0 3.4
3.1 Code maintenance / bug fixes 0.5 0.2 (ongoing) --
3.2 Pluggable back-end storage framework 2.5 2.2 27-Nov-2009 19-Nov-2009
3.3 Load/Save user interface improvement 1.0 1.0 27-Nov-2009 20-Nov-2009
3.4 Load/Save workspace browsing 3.0 -.- 27-Nov-2009 --

Task breakdowns

(effort estimates in days to nearest 0.25)

3.2: Pluggable storage framework

Implementation to be sufficient to pass the current load/save test suite.

Estimated effort: 2.5 days

  • (0.5) implement generic read-only interface plugin for local files (Done 16-Nov-2009/0.5)
  • (1.0) implement generic interface plugin for eXist AtomPub (Done 17-Nov-2009/0.8)
  • (0.5) update load workspace module to use the revised framework (Done 19-Nov-2009/0.5)
  • (0.5) update save workspace module to use the revised framework (Done 19-Nov-2009/0.5)

Actual effort: 2.2 days (for 2.5 planned activity)

3.3: Load/save workspace user interface improvement

Estimated effort: 1.0 days

  • (0.5) Implement simplified load/save user interface with dialogs, using the pluggable storage interface and presenting a single workspace URI rather than 3 fields,
  • (0.5) Work through and replace all direct references to AtomPub module, except those in the eXist pluggable storage module.

Actual effort: 1.0 days (for 1.0 planned activity)

3.4: User interface for workspace browsing

Estimated effort: 3.0 days

  • (0.25) check service document handling in eXist 1.4
  • (0.25) investigate Google Data API for loading/saving workspaces
  • (0.5) plan strategy to implement collection/workspace browsing via eXist
  • (1.0) implement browsing capability in eXist storage plug-in module
  • (1.0) add browse facility to load/save dialogs

Actual effort: 0 days (for 0 planned activity)

Sprint review notes

Finished cleaning up the underlying storage framework, but the user interface still needs some work.

Otherwise, focused on wrapping up the JISCRI development phase - online demo, screencast, etc.

A fair amount of time was taken up by other projects, including travel to the CRM workshop in Berlin.

End-of-sprint review

The demonstrator running from Google Code SVN has been enhanced to represent the current state of development, and the underlying framework has been significantly improved and stabilized. While the delivered functionality is less than had been intended, the project is in fairly good shape for ongoing development as part of the Shuffl project, and the basic ideas have been somewhat vindicated.

I did not make time to install the system on one of Chris Holland's machines, but still hope to do this soon.

Velocity

Tasks completed/effort spent: 4.3/6.5 = 0.66

Activity summary

Date: Monday, 16 November, 2009

Shuffl:
  • (0.2) sprint 7 review
  • (0.2) sprint 8 plan
  • (0.5) local file storage module (task 3.2, subtask done)
Misc:
  • (0.1) email catch-up

Date: Tuesday, 17 November, 2009

Shuffl:
  • (0.2) code fixes and clean-up (task 3.1)
  • (0.8) eXist atompub storage module (task 3.2, subtask completed)

Date: Wednesday, 18 November, 2009

Shuffl:
  • (0.2) Review and update sustainability plan; create and publish initial DOAP description file (task 1.3)
  • (0.2) Shuffl exit: start creating demonstration app (task 2.3)
  • (0.4) Shuffl loadworkspace using new storage framework (task 3.2, subtask done)
Claros:
  • (0.2) CLAROS meeting with ISIS rep to discuss possible commercial opportunities

Date: Thursday, 19 November, 2009

Shuffl:
  • (0.5) working on save workspace using new storage API
Misc:
  • (0.5) A tidal wave of relevant emails

Date: Friday, 20 November, 2009

Shuffl:
  • (1.0) Completed save workspace using new storage API

Date: Monday, 23 November, 2009

CLAROS:
  • (1.0) CIDOC CRM meeting

Date: Tuesday, 24 November, 2009

CLAROS:
  • (0.7) CIDOC CRM meeting
Shuffl:
  • (0.3) Meet with Chris Bizer, discuss linked data etc.

Date: Wednesday, 25 November, 2009

CLAROS:
  • (0.7) travel
Misc:
  • (0.3) various catch-up

Date: Thursday, 26 November, 2009

Shuffl:
  • (0.4) Screencast
ADMIRAL:
  • (0.3) Meeting with Sally Rumsey / Ben O'Steen
  • (0.3) Travel to meeting

Date: Friday, 27 November, 2009

ADMIRAL:
  • (1.0) JISC Programme meeting
Shuffl:
  • (0.5) Complete Shuffl screencast

Notes for wrapping up Shuffl

  • Finalize screencast as QT and WMV
  • Publish screencast, demo app
  • Final progress report
  • Expenses - Berlin, screencast s/w, ...
  • Final retrospective
  • Final project budget to David F