Sept 22nd

Self introduction.

Shared project ideas.

Decided on project ideas.


Sept 25th

Meeting 10:43am friday sept 25th Applied Science Building

Read over Assignment 2 pdf file. Started discussion of iGeo app.

-sorting out features.
-will have categorized countries
-landscape mode
-different difficulties
-users will have to get at least 5-8 of 10 countries to move on.
-will come up with a logo
-alex is working on map for game

Group decided to use: http://en.wikipedia.org/wiki/List_of_sovereign_states as country list.

Looking at example iphone apps.

Meeting Ended 11:20 AM


Sept 29th

Meeting started at 11:00AM

-Worked on requirement document up to features

-Discussed Design Implementations.

-Change list to http://en.wikipedia.org/wiki/List_of_countries_by_continent

Delegated Task to organize countries by difficulty Soni - N/S America and Oceania Nawin - Asia Tom - Europe Alex - Africa

Ended at 1:30pm


Oct 1st

Meeting started 3:45pm

-Worked on tutorial rough draft

-chose font

-categorized country list

-assigned work for design document Tom - Feature Priority Alex - Guidlines Nawin - System Diagram Angad - Data Requirment

Meeting Ended 5:00pm


Oct 5th

Meeting started 5:00pm

Updated Requirements Document

  • worked on feature list
  • updated introduction
  • made up screenshots for tutorial
  • non system requirements

Started Design Document

  • worked on uml diagrams

meeting ended 7:20PM


Oct 6th

Meeting started 11:30am

Updated Requirements Document

  • updated feature list
  • added glossary
  • updated non functional requirements
  • edited intro and intended audience

Started quality assurance plan

meeting ended 2:00PM


Oct 8th

Meeting started 1:30pm

Submitted Requirements Document

Worked on UML Diagrams

Design Document Guidlines

Data Requirements

Started quality assurance plan

meeting ended 4:30PM


Oct 13th

Meeting started at 11:30am

looked into cocos2d

more research on small sdk functions

studied objective C code

assigned work for research

Nawin absent due to illness

meeting ended 2:00pm


Oct 22nd

Meeting started 3:30pm

tile usage research done by Tom

sqlite database research done by Nawin

reorganized database layout

learned more about project management in objective C

Angad absent due to doctor's appointment

meeting ended 5:00


Oct 31st

Meeting started 11:00am

Finished drawing map of europe (~30 countries needed for V1)

completed database

very early version of database integration implemented as a separate program; can read, and write from our database within iPhone app

started implementing explore, played around with tile maps, look into opacity changes/~work around

zoom will not be dynamic, but preset views (zoom using buttons)

zoom will no longer be implemented in V1;

meeting ended 3:00pm


Nov 3rd

Meeting started 11:00am

revised earlier documents to reflect current changes

changed database format to include tileIds

implemented a very alpha version of explorer: map works, put boundaries, id recognition for countries

meeting ended 5:00pm


Nov 4th

Meeting started 4:00pm

Integrate Database in Application

meeting ended 2:00am


Nov 5th

Meeting started 11:00am

Commented Code/clean up

Added Backgrounds to menu

Changed text for first menu

Changed text for country name output

Created all the menus

Finalized Version 1

Recorded Video

Wrote up test cases

Updated Documentation

Practiced Presentation

meeting ended 5:00pm


===Dec 2nd=== 10:00pm

we finished the stuff. meeting ended 6:00am Dec 3rd