Support effort-driven scheduling #83

Open
GoogleCodeExporter opened this issue Jun 28, 2015 · 26 comments
Open

Support effort-driven scheduling #83

GoogleCodeExporter opened this issue Jun 28, 2015 · 26 comments

Comments

@GoogleCodeExporter
Copy link

In effort-driven scheduling a length of a task depends on the amount of 
required work (in man-days or man-hours) and availability of resources. 

The basic rules is:
* If a task requires 3 man-days and a person who is doing this task is 50% 
available then the task must become 6 days long. 

Previous requests from SF issue tracker:
http://sourceforge.net/tracker/?
func=detail&aid=1102159&group_id=72728&atid=535430
http://sourceforge.net/tracker/?
func=detail&aid=1186184&group_id=72728&atid=535430
http://sourceforge.net/tracker/?
func=detail&aid=1250233&group_id=72728&atid=535430

Original issue reported on code.google.com by dbarashev on 9 Feb 2010 at 5:23

@GoogleCodeExporter
Copy link
Author

I agree with the comments added to the previous issues of this one 
(http://sourceforge.net/tracker/index.php?func=detail&aid=1186184&group_id=72728
&atid=535430).
I'm evaluating Ganttproject for my team and this is a killer criteria. I've two 
contractors working only 60% and 4 developer working 80% for this project.

Original comment by sbaGoo...@gmx.net on 3 Jul 2010 at 8:28

@GoogleCodeExporter
Copy link
Author

I was also evaluating this tool, and am really missing this feature. I used to 
work with Twiddlebit Plan For Windows on my previous job, where we use this 
continuously. Tracking progress and/or validating estimated workload is very 
hard without this. 

Original comment by vslui...@yahoo.com on 4 Nov 2010 at 8:20

@GoogleCodeExporter
Copy link
Author

Issue 311 has been merged into this issue.

Original comment by dbarashev on 12 Oct 2011 at 6:45

@GoogleCodeExporter
Copy link
Author

What's the current status of this issue? Will it be solved some day soon?

Original comment by janh...@gmail.com on 21 Jan 2013 at 10:07

@GoogleCodeExporter
Copy link
Author

Same thing for me. I am very surprised this feature has not implemented yet. 
Unthinkable to work with a project management tool without.

Original comment by william....@gmail.com on 23 Feb 2013 at 10:30

@GoogleCodeExporter
Copy link
Author

This feature would be very helpful and save large amounts of time when trying 
to get close to a realistic schedule

Original comment by AlanClar...@gmail.com on 10 Apr 2013 at 1:13

@GoogleCodeExporter
Copy link
Author

Will it be implemented or i should look for another tool?

Original comment by pawel.bo...@gmail.com on 10 Sep 2013 at 9:33

@GoogleCodeExporter
Copy link
Author

Hello,

I also found this error a few months. The consequence is impossibility for me 
to use GanttProject ... what a shame.
It is essential that the end date of a task assigned to a partially missing 
resource is calculated correctly otherwise the project planning is distorted.
I hoped that version 2.6.2 include a patch ...
When this subject will be corrected ?

Thanking you.

Regards.
Kriss

Original comment by bouln...@essilor.fr on 7 Jan 2014 at 2:45

@GoogleCodeExporter
Copy link
Author

Issue 813 has been merged into this issue.

Original comment by dbarashev on 10 Feb 2014 at 11:01

@GoogleCodeExporter
Copy link
Author

Please support this feaure. I too require it, it's the mainstay of project 
plans which reflect real world workloads and would rather not look elsewhere, 
everything else on Ganttproject is near perfect.

Original comment by j...@anotherangler.net on 31 Mar 2014 at 10:47

@GoogleCodeExporter
Copy link
Author

I was just looking at switching to the gantt software but without effort driven 
scheduling and duration in hours it is practically worthless to me. please let 
me know if this has been added or will in the future because I like everything 
else so far. Thanks

Original comment by 21whitne...@gmail.com on 28 Jul 2014 at 3:39

@GoogleCodeExporter
Copy link
Author

Do you have any idea when this will be implemented? I keep getting back to your 
software, but this issue keeps killing my use of it. 

Original comment by vslui...@yahoo.com on 29 Oct 2014 at 11:08

@GoogleCodeExporter
Copy link
Author

You probably know that GanttProject is developed in spare time. All promises or 
estimates about when something will be implemented are wrong by definition, 
that's why you don't see any of them.

Original comment by dbaras...@ganttproject.biz on 29 Oct 2014 at 2:19

@GoogleCodeExporter
Copy link
Author

Clear enough :) Thanks for developing this, just hoped you could help out!

Original comment by lindakas...@gmail.com on 29 Oct 2014 at 6:26

@GoogleCodeExporter
Copy link
Author

Any movement on this request?

Original comment by jeremy.n...@gmail.com on 9 Jun 2015 at 9:35

This was referenced Jun 28, 2015
@JonSeagull
Copy link

I agree with the others...I was really loving this program until I hit the wall. No resource leveling at all? No effort driven task length? For me this went immediately from "best program ever!" to worthless.

@joacimsvensson
Copy link

joacimsvensson commented Dec 22, 2016

Agreed. No resource leveling and effort-driven scheduling kind of defeats the purpose of Ganttproject as a project MANAGEMENT tool.

I feels like something that should be a core functionality in any project management software. You have resources with allocated time, you have tasks - surely they should interact.

@CyrilleGuimezanes
Copy link

CyrilleGuimezanes commented Mar 2, 2018

Hello!
Up, this is absolutly necessary to make a real plannification...

@chuck990
Copy link

chuck990 commented Nov 5, 2020

Just wanted to add another +1 to the request for resource-focused / effort-driven scheduling. It would be a major upgrade

@daniberc
Copy link

Hello,

I was looking for an alternative to MS Project, and I was very entusiastic with GanttProject, until I reach this issue.

From my point of view, to manage a project based in tasks,, I need the tasks to be affected by the number of ressources working on it, and their availabilty.

If a task as a duration of 10 days, and I assigned 2 ressources to it, I need that this task is reduced to 5 days.
And if I assigned only 1 ressources with a 50% dedication, the duration of the task should be of 20 days.

This features is a deal breaker, and it has not to be linked with the issue of the day-offs.

Hoping this issue would be take in account shortly.

@AlexDG89
Copy link

Hello,

  • 1 for me. It was useful until I read this. Everyone defines tasks as effort-based non day-based. This is a major issue.

@silveira
Copy link

silveira commented Feb 21, 2022

+1

Even if a partial implementation of effort-driven scheduling would be great. For example, a resource have a certain limit of parallel tasks he can realistic work on it. Right now you can assign as many tasks as you want to a resource and they will all run in parallel. In my experience this really broke my use case for using GanttProject.

@vChavezB
Copy link

vChavezB commented Mar 12, 2022

I am interested in contributing to this feature but it would be nice if I could get the following info from the devs/mantainers:

  • Which source files are related to the options the user can modify via the Task property window?
  • Where is the task duration calculated? I saw something here but I am not sure.

@Exxerial
Copy link

+1 This issue has been ongoing since 2017 (5 years now). I think this is a major feature and should be priority task...

@Synochy
Copy link

Synochy commented Jul 13, 2022

+1 very interested by this feature

@TaniumOG
Copy link

+1

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment